Skip to content
City of Aspen Engineering Logo
  • Overview
  • Introduction
    • What is a CMP?
    • Why do we require a CMP?
    • CMP Enforcement Policy
  • Paperwork
    • Paperwork
    • Disturbance Area and Vicinity Map
    • Project Description, Permit List, Contact List
    • Public Notification and Signage
    • Dates and Hours of Construction
    • CRA/Core
    • Adjoining Properties
    • Project Fencing
    • Tree Permit
    • Section 2 Review
  • Site and ROW
    • Site and Right of Way Management
    • Site Plan
    • Earth Stabilization
    • ROW Management
    • Section 3 Review
  • Noise Suppression
    • Noise Suppression
    • Noise Limits and Measurements
    • Noise Monitoring
    • Continued Noise Regulations
    • Noise Suppression Plan
    • Noise Suppression Barrier Screening
    • Section 4 Review
  • Additional Requirements
  • Course Review
  • Final Exam



Every construction site must notify all neighbors within 300 feet of the site and provide them with a project description and schedule.


Notification must take place no less than 10 days prior to the start of construction. Project updates for the neighborhood shall continue on a no less than monthly basis.

Click Here to Continue

3.2-3.3 Public Notification and Signage

Public Notification and Signageavick2018-11-05T23:26:15+00:00
https://cmpaspen.com/wp-content/uploads/2018/11/public-notification_merged.mp3

City of Aspen

130 S. Galena Street Aspen, CO 81611

Phone: 970.920.5000

Email: Email for Info

Copyright City of Aspen Engineering  |  All Rights Reserved  |  Powered by Vick+Co
Facebook