Skip to content
City of Aspen Engineering Logo
  • Overview
  • Introduction
    • What is a CMP?
    • Why do we require a CMP?
    • CMP Enforcement Policy
  • Paperwork
    • Paperwork
    • Disturbance Area and Vicinity Map
    • Project Description, Permit List, Contact List
    • Public Notification and Signage
    • Dates and Hours of Construction
    • CRA/Core
    • Adjoining Properties
    • Project Fencing
    • Tree Permit
    • Section 2 Review
  • Site and ROW
    • Site and Right of Way Management
    • Site Plan
    • Earth Stabilization
    • ROW Management
    • Section 3 Review
  • Noise Suppression
    • Noise Suppression
    • Noise Limits and Measurements
    • Noise Monitoring
    • Continued Noise Regulations
    • Noise Suppression Plan
    • Noise Suppression Barrier Screening
    • Section 4 Review
  • Additional Requirements
  • Course Review
  • Final Exam


11.2 If your site is to have any earth stabilization (e.g. micro piles, soil nails, etc…) then your CMP must include an Earth Stabilization Plan.
Show the full extent of stabilization and excavation.


5.6 Surcharge: show all locations where heavy vehicles will be parked along the edge of the stabilized wall. Have approval from the engineer stating that the wall will support these vehicles in these locations.

Earth Stabilization

Click Here to Continue
Earth Stabilizationavick2018-11-05T23:14:12+00:00
https://cmpaspen.com/wp-content/uploads/2018/11/Earth-stabilization_merged.mp3

City of Aspen

130 S. Galena Street Aspen, CO 81611

Phone: 970.920.5000

Email: Email for Info

Copyright City of Aspen Engineering  |  All Rights Reserved  |  Powered by Vick+Co
Facebook